Industrial Asset Markets

 

 

Construction Sequencing

Client: Utah Department of Transportation (UDOT)

 

Cost Savings: $60,000

 

UDOT identified over 28 bridges that needed urgent repair throughout the State. Using traditional methods this work is time consuming and causes approximately 9 months of commuter traffic disruption per bridge.  UDOT wanted it done in one weekend... Read more

 

BART Station

Client: URS

Cost Savings: $80,000

URS was given a challenge to create a 3D model of a BART station and demonstrate how it would place flat screen monitors through out the station for advertising.  The challenge was to accomplish this in a two week time period... Read more

 

AS-Built Extraction

Client: Grunley

Cost Savings: $68,000~

The contractor is tasked with an AS-Built scan for a sub-floor that is above an accessible ceiling while the asset remains open for business. The contractor is not be able to examine the sub-floor for data collection and inspection prior to construction start, unless an un-invasive procedure can be found... Read more